on a new construction site an electrician can install a new light fixture in 20 minutes a project calls for 24 new fixtures to be installed on each of four floors if a work day is 8 hours how many work days will it take to electricians to complete the installations

Respuesta :

If there were two electricians, they'd need to install 48 fixtures per person.. if it takes 20 minutes for each fixture, it would take a total of 960 minutes, which converts to 16 hours. If a work day was only 8 hours, it would take two electricians TWO work days to install 96 light fixtures, or 24 light fixtures for four floors.